Citation: Lakeshore Group v Dep’t of Environmental Quality, 507 Mich 52; 968 NW2d 251 (2021). Decided May 20, 2021.
Summary. A developer could not extinguish neighboring property owners’ right to challenge a critical dune area permit by conveying narrow strips of land.
Background
A developer purchased a 130-acre parcel on the Lake Michigan shoreline in a critical dune area regulated by the sand dunes protection and management act (“SDPMA”), MCL 324.35301 et seq. The Department of Environmental Quality, now the Department of Environment, Great Lakes, and Energy (“EGLE”), issued the permits and a special exception needed to develop the property. MCL 324.35305(1) allows an aggrieved permit applicant or an aggrieved owner of property immediately adjacent to the proposed use to request a contested case hearing. Two adjacent property owners and a nonprofit association to which one of them belonged intervened in the resulting contested case. The developer then conveyed about 20 acres next to one owner’s property to a nature conservancy, along with other slivers of land. The developer argued that the conveyances meant the intervenors were no longer owners of immediately adjacent property. The administrative law judge dismissed the matter for lack of standing, and the Court of Appeals agreed that the intervenors had lost their petition rights.
Holding
The Court reversed. MCL 324.35305(1) balances preservation of critical dunes against economic development by permitting two groups to request a contested case hearing. Those groups are aggrieved permit applicants and aggrieved owners of property immediately adjacent to the proposed use. The parties agreed that the adjacent owners had petition rights when they moved to intervene. The statute creates a two-step process in which an eligible party requests a hearing and the department then conducts a contested case hearing under the Administrative Procedures Act, MCL 24.201 et seq. The statute contains no intermediate step that permits EGLE to deny a hearing to a party who was eligible when the request was made and who still wishes to proceed. Nothing in the statute provides that a party who has exercised its petition rights may later be divested of them. The statutory criteria are threshold requirements for requesting a hearing, and there is no basis for requiring a petitioner to maintain that status throughout the proceedings. The developer’s later sales of land therefore did not extinguish the petition rights.
Significance
The statutory protections for critical dune areas may not be circumvented through strategic conveyances of property.
Opinions
Chief Justice McCormack wrote for the majority, joined by Justices Bernstein, Clement, and Cavanagh. Justices Zahra and Viviano each dissented. Justice Welch did not participate.
Citation
Lakeshore Group v Dep’t of Environmental Quality, 507 Mich 52; 968 NW2d 251 (2021). Decided May 20, 2021. Read the full opinion (PDF) from the Michigan Supreme Court.
This summary is provided for general information about developments in Michigan law. It does not constitute legal advice. Readers should consult the full opinion because the case may be subject to further proceedings.