In re Application of Consumers Energy Co for Reconciliation

Citation:  In re Application of Consumers Energy Co for Reconciliation, 350 Mich App 199; 32 NW3d 471; 2024 WL 387090 (2024) (Docket No. 362931).  Decided February 1, 2024.

Summary.  Consumers Energy could not pass on to customers the increased power supply costs caused by its imprudent management of a prolonged generating unit outage.

Background

Michigan utilities estimate power supply costs in setting rates and later apply to the Public Service Commission (“PSC”) to reconcile actual costs.  Recovery of under-recovered costs depends on reasonable and prudent management.  Consumers Energy Company sought to recover costs tied to an extended outage of a generating unit.  The PSC disallowed the costs associated with the extension of the outage.

Holding

The Court of Appeals affirmed.  The Court held that the record confirmed that Consumers provided unreasonable or imprudent management of the outage and caused the increased costs it sought to recover.  In re Application of Consumers Energy Co for Reconciliation, 350 Mich App 199 (2024).  The PSC did not err in modifying the reconciliation plan.  Id.

Significance

Utility customers do not have to pay for costs caused by a utility’s own imprudence.

Opinions

Judge Brock A. Swartzle wrote for a unanimous panel that included Judges Stephen L. Borrello and Sima G. Patel.

Citation

In re Application of Consumers Energy Co for Reconciliation, 350 Mich App 199; 32 NW3d 471; 2024 WL 387090 (2024) (Docket No. 362931).  Decided February 1, 2024.  Read the full opinion (PDF) from the Michigan Court of Appeals.