Citation: Seven County Infrastructure Coalition v Eagle Co, 605 US 168; 145 S Ct 1497; 221 L Ed 2d 820 (2025) (Docket No. 23-975). Decided May 29, 2025.
Summary. The United States Supreme Court held that courts must give agencies substantial deference in reviewing environmental impact statements under the National Environmental Policy Act (“NEPA”) and that NEPA does not require an agency to study the effects of separate upstream and downstream projects.
Background
New railroad construction requires approval from the Surface Transportation Board. 49 USC 10901. In 2020 the Seven County Infrastructure Coalition sought approval of an 88-mile rail line connecting Utah’s oil-rich Uinta Basin to the national rail network. The Board prepared a 3,600-page environmental impact statement after collecting more than 1,900 comments. It declined to analyze in detail the environmental effects of increased oil drilling upstream and refining along the Gulf Coast downstream. The United States Court of Appeals for the District of Columbia Circuit vacated the approval.
Holding
The Court reversed and remanded. NEPA is a purely procedural statute that prescribes the necessary process but does not mandate particular results. Robertson v Methow Valley Citizens Council, 490 US 332, 350; 109 S Ct 1835; 104 L Ed 2d 351 (1989). Courts reviewing an environmental impact statement must afford the agency substantial deference on questions of scope and detail. NEPA focuses on the proposed action under review. 42 USC 4332(2)(C). An agency need not evaluate the effects of separate projects outside its regulatory authority. Dep’t of Transp v Public Citizen, 541 US 752, 767; 124 S Ct 2204; 159 L Ed 2d 60 (2004). Courts may not use NEPA review to delay or block projects based on the effects of other projects. Vermont Yankee Nuclear Power Corp v Natural Resources Defense Council, Inc, 435 US 519, 558; 98 S Ct 1197; 55 L Ed 2d 460 (1978).
Significance
The decision significantly narrows NEPA litigation against infrastructure projects. Agencies have greater latitude to limit the scope of environmental review.
Opinions
Justice Kavanaugh wrote the opinion of the Court joined by Chief Justice Roberts and Justices Thomas, Alito, and Barrett. Justice Sotomayor filed an opinion concurring in the judgment joined by Justices Kagan and Jackson. Justice Gorsuch did not participate. The concurrence is not binding precedent.
Briefs
- Petition for a writ of certiorari (filed March 4, 2024)
- Brief of federal respondents in opposition (filed May 20, 2024)
- Brief of respondents Eagle County, Colorado, et al. in opposition (filed May 20, 2024)
- Reply of petitioners Seven County Infrastructure Coalition, et al. (filed May 28, 2024)
- Brief of petitioners Seven County Infrastructure Coalition, et al. (filed August 28, 2024)
- Joint appendix (filed August 28, 2024)
- Brief of federal respondents in support of petitioners (filed August 28, 2024)
- Joint appendix (Corrected version of Volume I) (Oct. 22, 2024 (filed August 28, 2024)
- Brief of respondent Eagle County, Colorado (filed October 18, 2024)
- Brief of respondents Center for Biological Diversity, et al. (filed October 18, 2024)
- Reply of petitioners Seven County Infrastructure Coalition, et al. (filed November 18, 2024)
- Reply of federal respondents supporting petitioners (filed November 18, 2024)
- Amicus curiae briefs (35) are available on the Supreme Court docket
Oral Argument
- Oral argument audio and transcript (Supreme Court of the United States)
Citation
Seven County Infrastructure Coalition v Eagle Co, 605 US 168; 145 S Ct 1497; 221 L Ed 2d 820 (2025) (Docket No. 23-975). Decided May 29, 2025. Read the full opinion (PDF) from the United States Supreme Court.
This summary is provided for general information about developments in federal law. It does not constitute legal advice. Readers should consult the full opinion because the case may be subject to further proceedings.